NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
48 CFR Parts 1807 and 1815
Revision to NASA FAR Supplement Coverage on Procurement Plans,
Instructions for Technical Proposal and Business Management Proposal
Submissions, and Contents of the Prenegotiation Position Memorandum
AGENCY: Office of Procurement, Procurement Policy Division, National
Aeronautics and Space Administration (NASA).
ACTION: Notice of proposed rulemaking.
-----------------------------------------------------------------------
SUMMARY: This rule proposes to amend the regulations pertaining to
procurement plans, the instructions for technical and business
management proposals, and the contents of the prenegotiation position
memorandum in order to emphasize the importance of facilities in the
contract planning and decision making process.
DATES: Comments must be received on or before July 11, 1994.
ADDRESSES: Submit comments to Mr. Joseph Le Cren, Contract Pricing and
Finance Division (Code HC), Office of Procurement, NASA Headquarters,
Washington, DC 20546. Comments on the paperwork burden should also be
addressed to the Office of Information and Regulatory Affairs of OMB,
Attention: Desk Officer for NASA, Washington, DC 20503.
FOR FURTHER INFORMATION CONTACT:
Mr. Joseph Le Cren, (202) 358-0444.
SUPPLEMENTARY INFORMATION:
Background
Over the last several years, NASA's Office of the Inspector General
has issued several reports critical of the agency and its contractors
regarding facilities leasing practices. One report addressed the issue
on an agency-wide basis. That report stated that NASA was paying
several times over for the same facilities due to contractors entering
into a series of short-term leases. The proposed rule emphasizes the
importance of facilities by requiring installation procurement plans
address facilities, specifying the information needed from contractors
in their business management plans for the agency to properly evaluate
the proposed costs, and requiring that the prenegotiation memorandum
discuss the factors considered in the evaluation of facilities. The
proposed rule also revises the current coverage on procurement plans
requiring Headquarters approval to better address the major facilities
issues which should be considered.
Impact
NASA certifies that this regulation will not have a significant
economic impact on a substantial number of small entities under the
Regulatory Flexibility Act (5 U.S.C. 601 et seq.). The information
collection requirements in this proposed rule have been submitted to
the Office of Management and Budget for review under 44 U.S.C. 3504(h).
The information will be used by NASA contracting personnel and
technical personnel to evaluate and select proposals for contracts over
$1,000,000. If this information is not collected, NASA will be less
able to evaluate contract costs and ensure that those costs are fair
and reasonable. The estimated annual paperwork burden of 300 hours in
calculated by multiplying the estimated number of respondents (300) by
the estimated hours (1 hour) for each respondent to prepare the
information.
List of Subjects in 48 CFR Part 1807 and 1815
Government procurement.
Tom Luedtke,
Deputy Associate Administrator for Procurement.
Accordingly, 48 CFR parts 1807 and 1815 are proposed to be amended
as follows:
1. The authority citation for 48 CFR parts 1807 and 1815 continues
to read as follows:
Authority: 42 U.S.C. 2473 (c)(1).
PART 1807--ACQUISITION PLANNING
2. Section 1807.170-1 is amended by revising paragraph (b)(10)(i)
to read as follows:
180.170-1 Procurement plans requiring approval by NASA Headquarters.
* * * * *
(b) * * *
(10) Item 10. Contractor-owned or leased and Government-furnished
property. (i) If the proposed contract period of performance (exclusive
of options) will be for a shorter period than the useful life, for the
program, of any required contractor-owned or leased facilities (as
defined in (FAR) 48 CFR 45.301), the facilities are unlikely to be
needed by the contractor for any purpose other than the program effort
being contracted for, and the facilities will represent a significant
cost to the contract, then the procurement plan shall discuss the
feasibility of the Government acquiring the right to use the facilities
for longer than the proposed contract period, as well as the proposed
procurement strategy for accomplishing this use.
(A) If program uncertainties for continuing beyond the contract
period of performance (exclusive of options) are significant, it may be
in the Government's best interests to acquire use of the facilities
during only that time. This strategy may make the facilities more
costly to the Government for the contract period than if a contractual
arrangement for longer use were made. However, it should reduce the
program risks associated with longer-term Government facilities
obligations;
(B) If the program uncertainties for continuing beyond the contract
period of performance (exclusive of options) are not significant, it
may be in the Government's best interests to acquire the right to use
the facilities for longer than the proposed contract period of
performance (exclusive of options) in order to take advantage of
economies in long-term facilities investment. In such cases, the
following shall be considered:
(1) Whether the amount of the potential cost savings to the
Government arising from the contractor entering into a long-term
arrangement (lease, purchase or construction) continuing beyond the
contract period of performance (exclusive of options) could be
significant;
(2) If a long-term investment by the contractor could result in
significant cost savings to the Government, the type of long-term
arrangement that is believed would be most appropriate (e.g., long-term
lease with the right of assignment to a third party or the Government,
at the Government's option; purchase or construction of the facilities,
with depreciation and cost of money either accelerated to cover the
contract period of performance (exclusive of options) or over the
useful life of the facilities); and
(3) Whether the contractor might require a financial guarantee be
provided by the Government in order to enter into a long-term
arrangement and, if so, what the potential amount of such a guarantee
might be, should the contract end (e.g., options are not exercised, or
the contractor is not selected in a recompetition).
* * * * *
3. Section 1807.170-2 is revised to read as follows:
1807.170-2 Procurement plans requiring approval at the installation
level.
Procurement plans prepared for installation-level approval shall be
prepared in accordance with 1807.170-1 or in the format prescribed by
the installation. Installation prescribed formats shall ensure all
contract management considerations enumerated at 1807.170-1(c) are
addressed. In addition, installation prescribed formats shall ensure
that plans for procurements in excess of $2,500,000 address the
considerations at 1807.170-1(b)(10).
PART 1815--CONTRACTING BY NEGOTIATION
4. Section 1815.406-70 is amended by republishing paragraph (b)
introductory text and paragraph (b)(5) introductory text and revising
paragraph (b)(5)(iii) to read as follows:
1815.406-70 Instructions for technical proposal and business
management proposal submission.
(a) * * *
(b) Business management proposal. Proposals should include the
following:
* * * * *
(5) A statement as to--
* * * * *
(iii) The cost of any additional facilities (as defined at (FAR) 48
CFR 45.301) required to perform the work and how the costs are to be
charged, with information as to whether the facilities will be
contractor-furnished or Government-furnished and, if contractor-
furnished, the alternatives considered (e.g., short-term lease, long-
term lease with option to transfer the lease to a third party,
purchase), including the long and short term benefits of each
alternative, a description of any unique requirements or arrangements
involved with each alternative, as well as the reasons for the
alternative selected, a copy of the proposed lease or purchase
agreement, identification of all costs included in the lease and
ownership alternatives considered; and
* * * * *
5. Paragraph (c)(5) of section 1815.807-70 is revised to read as
follows:
1815.807-70 Content of the prenegotiation position memorandum.
* * * * *
(c) * * *
(5) Contractor/Government investment in facilities and equipment
(and any modernization to be provided by the contractor/Government).
Although not all inclusive, the following are to be covered:
(i) The facilities needed by the contractor;
(ii) How the facilities are to be provided (Government or
contractor);
(iii) If to be provided by the contractor, the alternatives
considered (operating lease, capital lease, contractor purchase or
construction, or other alternatives);
(iv) Whether a financial guarantee has been requested by the
offeror;
(v) The reasons for the alternative selected; and
(vi) How the costs are to be charged.
* * * * *
[FR Doc. 94-11144 Filed 5-9-94; 8:45 am]