[Federal Register Volume 63, Number 98 (Thursday, May 21, 1998)]
[Notices]
[Pages 27938-27939]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-13496]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-531-000]
NorAm Gas Transmission Company; Notice of Request Under Blanket
Authorization
May 15, 1998.
Take notice that on May 11, 1998, NorAm Gas Transmission Company
(NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket No.
CP98-531-000 a request pursuant to Sections
[[Page 27939]]
157.205 and 157.211 of the Commission's Regulations under the Natural
Gas Act (18 CFR 157.205, 157.211) for authorization to construct and
operate certain facilities in Webster Parish, Louisiana, under NGT's
blanket certificate issued in the Docket No. CP82-384-000 and CP82-384-
001 pursuant to Section 7 of the Natural Gas Act, all as more fully set
forth in the request that is on file with the Commission and open to
public inspection.
NGT specifically requests authority to install a 3-inch tap, 3-inch
regulatory setting, and 6-inch meter station, on NGT's Line S in
Webster Parish, Louisiana, under Subpart G of Part 284 of the
Commission's Regulation. NGT states that this meter station is being
constructed to provide service to Arkla, a distribution division of
NorAm Energy Corp. (Arkla). NGT states the estimated volumes to be
delivered through these facilities are approximately 3,008,086 MMBtu
annually and 14,857 MMBtu on a peak day. NGT states the cost of the
facilities to be installed is $64,198, and that $59.375 will be
reimbursed by Arkla. NGT also states that Arkla will install 550 feet
of 6-inch pipe to connect this point to an addition to its Louisiana
distribution system which it is acquiring from Louisiana-Nevada Gas
Transit Company.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-13496 Filed 5-20-98; 8:45 am]
BILLING CODE 6717-01-M