98-13496. NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 98 (Thursday, May 21, 1998)]
    [Notices]
    [Pages 27938-27939]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-13496]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-531-000]
    
    
    NorAm Gas Transmission Company; Notice of Request Under Blanket 
    Authorization
    
    May 15, 1998.
        Take notice that on May 11, 1998, NorAm Gas Transmission Company 
    (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket No. 
    CP98-531-000 a request pursuant to Sections
    
    [[Page 27939]]
    
    157.205 and 157.211 of the Commission's Regulations under the Natural 
    Gas Act (18 CFR 157.205, 157.211) for authorization to construct and 
    operate certain facilities in Webster Parish, Louisiana, under NGT's 
    blanket certificate issued in the Docket No. CP82-384-000 and CP82-384-
    001 pursuant to Section 7 of the Natural Gas Act, all as more fully set 
    forth in the request that is on file with the Commission and open to 
    public inspection.
        NGT specifically requests authority to install a 3-inch tap, 3-inch 
    regulatory setting, and 6-inch meter station, on NGT's Line S in 
    Webster Parish, Louisiana, under Subpart G of Part 284 of the 
    Commission's Regulation. NGT states that this meter station is being 
    constructed to provide service to Arkla, a distribution division of 
    NorAm Energy Corp. (Arkla). NGT states the estimated volumes to be 
    delivered through these facilities are approximately 3,008,086 MMBtu 
    annually and 14,857 MMBtu on a peak day. NGT states the cost of the 
    facilities to be installed is $64,198, and that $59.375 will be 
    reimbursed by Arkla. NGT also states that Arkla will install 550 feet 
    of 6-inch pipe to connect this point to an addition to its Louisiana 
    distribution system which it is acquiring from Louisiana-Nevada Gas 
    Transit Company.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-13496 Filed 5-20-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
05/21/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-13496
Pages:
27938-27939 (2 pages)
Docket Numbers:
Docket No. CP98-531-000
PDF File: