96-14347. NorAm Gas Transmission Company, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 61, Number 111 (Friday, June 7, 1996)]
    [Notices]
    [Pages 29089-29092]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-14347]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-519-000, et al.]
    
    
    NorAm Gas Transmission Company, et al.; Natural Gas Certificate 
    Filings
    
    May 31, 1996.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. NorAm Gas Transmission Company
    
    [Docket No. CP96-519-000]
    
        Take notice that on May 13, 1996, as supplemented on May 28, 1996, 
    NorAm Gas Transmission Company (NGT), 1600 Smith Street, Houston, Texas 
    77002, filed in Docket No. CP96-519-000, a request pursuant to Sections 
    157.205, 157.211 and 157.216 of the Commission's Regulations under the 
    Natural Gas Act (18 CFR 157.205, 18 CFR 157.211, and 157.216) for 
    authorization under its blanket certificate issued in Docket Nos. CP82-
    384-000 and CP82-384-001, pursuant to Section 7 of the Natural Gas Act, 
    to abandon certain facilities in Arkansas and Louisiana and to operate 
    their existing replacement facilities as jurisdictional facilities to 
    provide transportation services under Subpart G of Part 284 of the 
    Commission's regulations, all as more fully set forth in the request 
    which is on file with the Commission and open to public inspection.
        NGT requests authority, pursuant to 18 CFR 157.216, to abandon one 
    2-inch tap and 2-inch U-Shape meter station located on NGT's N Line in 
    Caddo Parish, Louisiana. NGT relates that these facilities were 
    originally installed in 1952, and certificated in Docket No. G-252, to 
    serve ARKLA, a distribution division of NorAM Energy Corp. (ARKLA). 
    Additionally, NGT requests authority, pursuant to 18 CFR 157.216, to 
    abandon two 1-inch first-cut regulators located on NGT's Line TM-3 in 
    Hot Spring County, Arkansas. NGT relates that these facilities were 
    originally installed in 1967, and certificated in Docket No. CP67-83-
    000, to serve ARKLA. NGT says no service is to be abandoned, and the 
    abandoned facilities will be reclaimed.
        NGT seeks authority to operate the existing 4-inch tap and 4-inch 
    Skid-mounted meter station (which replaced the one 2-inch tap and 2-
    inch U-Shape meter station) on NGT's Line N in Section 30, Township 17 
    North, Range 14 West, Caddo Parish, Louisiana in order to provide 
    transportation services under Subpart G of Part 284 of the Commission's 
    regulations. NGT states that these facilities were installed in April 
    1996, solely to provide services authorized under Section 311 of the 
    NGPA and Subpart B of the Commission's regulations, to serve ARKLA's 
    request for increased volumes. NGT states the estimated volumes to be 
    delivered are approximately 127,000 MMBtu annually and 400 MMBtu on a 
    peak day on an interruptible basis. NGT says these facilities were 
    constructed at an estimated cost of $24,193 and ARKLA will reimburse 
    NGT the total construction cost.
        NGT seeks authority to operate two existing 1-inch Moonne first-cut 
    regulators (which replaced the two 1-inch first-cut regulators) located 
    on NGT's Line TM-3 in Section 16, Township 4 South, Range 16 West, Hot 
    Spring County, Arkansas in order to provide transportation services 
    under Subpart G of Part 284 of the Commission's regulations. NGT states 
    these facilities were installed in March 1996, solely to provide 
    services authorized under Section 311 of the NGPA and Subpart B of the 
    Commission's regulations to serve ARKLA's distribution customers at its 
    existing Malvern Town Border Station. NGT states the estimated volumes 
    to be delivered through these facilities are
    
    [[Page 29090]]
    
    approximately 1,460,000 MMBtu annually and 4,000 MMBtu on a peak day on 
    an interruptible basis. NGT says that the facilities were constructed 
    at an estimated cost of $6,834, and ARKLA will reimburse NGT $5,150 of 
    the construction cost.
        Comment date: July 15, 1996, in accordance with Standard Paragraph 
    G at the end of this notice.
    
    2. UtiliCorp Pipeline Systems, Inc., Complainant, v. Panhandle Eastern 
    Pipe Line Company, Respondent
    
    [Docket No. CP96-538-000]
    
        Take notice that on May 23, 1996, UtiliCorp Pipeline Systems, Inc. 
    (UPL), 10700 East 350 Highway, Kansas City, Missouri, 64138, filed a 
    complaint in Docket No. CP96-538-000, pursuant to Section 5 of the 
    Natural Gas Act and Rule 206 of the Commission's Rules of Practice and 
    Procedure. UPL charges that Panhandle Eastern Pipe Line Company 
    (Panhandle) has acted in an unduly discriminatory and anticompetitive 
    manner, and requests that Panhandle be ordered to provide an 
    interconnection in Cass County, Missouri, with facilities to be owned 
    by UPL's intrastate pipeline subsidiary, Missouri Pipeline Company 
    (Missouri Pipeline), all as more fully set forth in the complaint which 
    is on file with the Commission and open to public inspection.
        UPL also requests that, to the extent that the Commission finds 
    that additional procedures, such as a show cause proceeding or an 
    evidentiary hearing, are required to resolve the complaint, its 
    complaint be consolidated with the previously filed complaints against 
    Panhandle by Missouri Gas Energy (MGE) in Docket No. CP95-755 and by 
    Mid Continent Market Center in Docket No. CP96-270. UPL states that the 
    evidentiary record is more developed in those proceedings and they 
    involve nearly identical facts and legal questions as represented in 
    UPL's complaint.
        Missouri Pipeline, a wholly-owned subsidiary of UPL, plans to 
    acquire an abandoned oil pipeline and to convert a portion of the line 
    to natural gas service as an intrastate pipeline extending about 32 
    miles from a point near Freeman, Missouri to a terminus near Sugar 
    Creek in Jackson County, Missouri. Missouri Pipeline will use this 
    pipeline, referred to as the Hawthorne project, to provide high 
    pressure natural gas service to the Kansas City Power & Light Company 
    Hawthorne Power Plant. The Hawthorne project will also have several 
    other delivery points into MGE's local distribution system.
        UPL states that it requested that Panhandle provide an 
    interconnection with the Hawthorne project facilities, and offered to 
    pay all the costs of the interconnection. UPL states that Panhandle 
    responded that unless UPL had incremental firm transportation 
    agreements for service into the Hawthorne project facilities, Panhandle 
    would not allow an interconnection. UPL avers that Panhandle has, at 
    other times and places, been willing to provide interconnections for 
    interruptible service to end-users, but refuses to provide 
    interconnections for potential competitors such as UPL, MGE, and Mid 
    Continent Market Center.
        Comment date: June 21, 1996, in accordance with the first paragraph 
    of Standard Paragraph F at the end of this notice. Answers to the 
    Complaint shall also be due on or before June 21, 1996.
    
    3. Panhandle Eastern Pipe Line Company
    
    [Docket No. CP96-542-000]
    
        Take notice that on May 24, 1996, Panhandle Eastern Pipe Line 
    Company (Panhandle), P.O. Box 1642, Houston, Texas 77251 filed in 
    Docket No. CP96-542-000, a petition pursuant to Section 16 of the 
    Natural Gas Act (NGA) and Rule 207(a)(2) of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.207 (a)(2)), for a declaratory order 
    concerning the present and future jurisdictional status of Mid 
    Continent Market Center, Inc. (Mid Continent). Panhandle's reasons for 
    its request are all more fully set forth in the petition which is on 
    file with the Commission and open to public inspection.
        Mid Continent was granted an NGA Section 1(c) ``Hindshaw'' 
    exemption and a Section 284.224 Blanket Certificate by the Commission 
    in 1995, see order at 72 FERC para. 62,274. Mid Continent has a 
    complaint pending with the Commission against Panhandle in Docket Nos. 
    CP96-270-000 and 001, see notices at 61 FR 18132 and 61 FR 25854. The 
    complaint(s) concerns Panhandle's interconnection with KN Interstate 
    Transmission Company's (KN Interstate) Haven Line pipeline segment in 
    Reno County, Kansas. Mid Continent intends to buy the Haven Line from 
    KN Interstate and construct a 9-mile pipeline segment to connect its 
    system to the Haven Line.
        Once such facilities are constructed and such pipeline 
    interconnections are available to Mid Continent, Panhandle says that 
    Mid Continent will no longer qualify for its Hindshaw exemption, 
    because Mid Continent will be able to, and intends to, transport 
    natural gas in interstate commerce for ultimate consumption outside the 
    state of Kansas. Panhandle furthers says that Mid Continent will then 
    have to file with the Commission for various certificate authorizations 
    under Section 7 of the NGA, if it wants to initiate such interstate 
    transportation services. Panhandle says that Mid Continent will have an 
    unfair competitive advantage over jurisdictional interstate pipelines 
    who have substantially more regulatory requirements, if Mid Continent 
    is allowed to continue to operate under its Hindshaw exemption.
        Panhandle petitions the Commission to make a finding that Mid 
    Continent will no longer qualify for its Hindshaw exemption from the 
    Commission's jurisdiction, and that Mid Continent will become a 
    ``natural gas company'' subject to the Commission's jurisdiction, if 
    Mid Continent completes its purchase of the Haven Line. Panhandle also 
    wants the Commission to confirm that as a natural gas company, Mid 
    Continent cannot continue its interstate operations unless it is 
    granted:
        (1) A Section 7(c) certificate to acquire the Haven Line;
        (2) A Section 7(c) certificate to construct and/or operate any 
    facilities connected to the Haven Line;
        (3) A Section 284.221 Blanket Certificate; and,
        (4) Approval of a Part 284 open access FERC Gas Tariff.
        Further, Panhandle suggests that Mid Continent may be presently 
    providing substantial interstate transportation service between various 
    interstate pipelines within the state of Kansas, rather than interstate 
    transportation service for its parent company, Western Resources, Inc., 
    a local distribution company (LDC) in Kansas, and that LDC's customers. 
    Panhandle says that Mid Continent's Hindshaw exemption was based on the 
    later and intimates that Mid Continent's Hindshaw exemption may already 
    be in jeopardy in light of the various recent Commission rulings cited.
        Comment date: June 21, 1996, in accordance with the first paragraph 
    of Standard Paragraph F at the end of this notice.
    
    4. Transcontinental Gas Pipe Line Corporation
    
    [Docket No. CP96-545-000]
    
        Take notice that on May 29, 1996, Transcontinental Gas Pipe Line 
    Corporation (Transco), P. O. Box 1396, Houston, Texas 77251, filed in 
    Docket No. CP96-545-000 an application pursuant to Section 7(c) of the 
    Natural Gas Act for a certificate of public convenience and necessity 
    for authorization to construct and operate
    
    [[Page 29091]]
    
    certain pipeline facilities on Transco's system in order to create 
    additional firm transportation capacity of the dekatherm equivalent of 
    115,000 Mcf of gas per day (Mcf/d) from points of receipt on Transco's 
    Leidy Line to points of delivery in Transco's Northeast Market area by 
    a proposed in-service date of November 1, 1997 (the SeaBoard Expansion 
    Project), all as more fully set forth in the application which is on 
    file with the Commission and open to public inspection.
        Transco states that the firm transportation service under the 
    SeaBoard Expansion Project will be provided to seven shippers under 
    Rate Schedule FT of Transco's FERC Gas Tariff, Volume No. 1, and 
    Transco's blanket certificate under Part 284(G) of the Commission's 
    regulations, and therefore, the SeaBoard firm transportation service 
    will be subject to the terms and conditions of Transco's tariff as 
    amended from time-to-time. Transco states that the Seaboard shippers 
    have committed to firm transportation service for terms ranging from 15 
    to 21 years subject to the receipt of necessary regulatory approvals 
    (including rolled-in rates) and the construction of the necessary 
    facilities. It is stated that the SeaBoard Expansion Project will 
    provide SeaBoard shippers with access to diverse natural gas supply 
    sources at the Leidy area, including but not limited to, gas supplies 
    sources on three interconnecting pipelines, purchased from suppliers, 
    or delivered from third party storage providers at Leidy, Pennsylvania.
        In order to provide the firm transportation service to the SeaBoard 
    shippers, Transco proposes to construct, install and operate five 
    pipeline loop segments and add a 15,000 horsepower (hp) compressor at 
    its existing Compressor Station No. 205.
        Transco states that it conducted an open season from August 7 
    through September 6, 1995, during which requests were accepted for up 
    to 115,000 Mcf/d of firm transportation from points of receipt on 
    Transco's Leidy Line to most points of delivery on the Transco system. 
    As a result of the open season, Transco contends that it executed 
    precedent agreements with seven shippers for a total of 115,000 Mcf/d 
    of firm transportation capacity, fully subscribing the project. It is 
    stated that the list of shippers participating in the SeaBoard 
    Expansion Project and their corresponding transportation quantities and 
    contract terms are set forth in the following table.
    
    ------------------------------------------------------------------------
                                                                 Total      
                                                Contract    transportation  
                     Shipper                      term     contract quantity
                                                 (Yrs)          (Mcf/d)     
    ------------------------------------------------------------------------
    Delmarva Power & Light Company...........         20               5,000
    Enron Capital & Trade Resources Corp.....         15              28,985
    Penn Fuel Gas, Inc.......................         20               1,500
    Pennsylvania Gas & Water Company.........         20              39,515
    Renaissance Energy, Inc..................         15              15,000
    Sun Company, Inc.........................         21              15,000
    Union Pacific Fuels, Inc.................         15              10,000
                                              ------------------------------
        Total................................  .........             115,000
    ------------------------------------------------------------------------
    
        Consistent with the Commission's Statement of Policy and after the 
    facilities necessary to serve the market for the Project had generally 
    been determined, Transco states that it solicited permanent capacity 
    relinquishment offers to be effective on November 1, 1997 from existing 
    shippers not submitting open season nominations to reduce the costs of 
    the SeaBoard Expansion Project, to prevent the construction of 
    unnecessary facilities, and to make use of unwanted firm capacity on 
    the Transco system. Transco states that it received permanent capacity 
    release offers from The Brooklyn Union Gas Company and Williams Energy 
    Services Company (WESCO). Transco further states that it determined 
    that the capacity offered in these release offers would not reduce the 
    facilities required to provide firm service to the SeaBoard shippers. 
    In addition, it is stated that the release capacity offered by WESCO 
    was located outside the capacity path of the Project. Transco avers 
    that it also received conditional capacity release offers from Public 
    Service Electric & Gas Company (PSE&G) and UGI Utilities, Inc. (UGI) 
    which were expressly contingent upon those shippers receiving an 
    equivalent amount of firm transportation service in the SeaBoard 
    Expansion Project. It is stated that the conditional nature of the 
    capacity release offers was contrary to the Commission's Statement of 
    Policy and to the purpose for which Transco solicited these offers 
    which was to make use of unwanted firm transportation capacity on the 
    system. Transco states that PSE&G and UGI were given the opportunity of 
    either participating in the SeaBoard Expansion Project or offering 
    permanently released capacity on an unconditional basis; however, both 
    PSE&G and UGI declined.
        In order to create the 115,000 Mcf/d of capacity to provide firm 
    transportation service to the SeaBoard shippers, Transco proposes to 
    construct and operate the following facilities:
        (1) 10.57 miles of 36-inch diameter pipeline loop beginning at 
    milepost 161.29 in Lycoming County, Pennsylvania and ending at milepost 
    171.86 in Clinton County, Pennsylvania.
        (2) 6.67 miles of 36-inch diameter pipeline loop beginning at 
    milepost 142.74 in Lycoming County, Pennsylvania and ending at milepost 
    149.41 in Lycoming County, Pennsylvania.
        (3) 5.46 miles of 42-inch diameter pipeline loop beginning at 
    milepost 1802.73 in Middlesex County, New Jersey and ending at milepost 
    1808.19 in Union County, New Jersey.
        (4) 7.10 miles of 36-inch diameter pipeline loop beginning at 
    milepost 18.96 in Burlington County, New Jersey and ending at milepost 
    26.06 in Burlington County, New Jersey.
        (5) The replacement of an existing 6.3 miles of 12-inch diameter 
    pipeline loop beginning at milepost 30.53 and ending at milepost 36.83 
    in Burlington County, New Jersey, with a 36-inch diameter pipeline 
    loop. The 12-inch pipeline segment will be removed and the 36-inch 
    replacement pipeline will be installed in the same trench.
        (6) The addition of a new 15,000 hp, electric motor-driven 
    compressor unit at Transco's existing Compressor Station 205 located at 
    milepost 1773.30 in Mercer County, New Jersey.
        (7) Modifications to the existing Milltown regulator station 
    located at milepost 1790.84 in Middlesex, New Jersey, to increase the 
    discharge
    
    [[Page 29092]]
    
    pressure into Transco's mainline E to 800 psig.
        (8) Modifications to the existing Linden regulator station located 
    at milepost 1808.19 in Union County, New Jersey, to reduce the pressure 
    in Transco's 42-inch Mainline E from 800 psig to 638 psig.
        (9) Addition of a 12-inch tap on Transco's existing Mainline A at 
    milepost 1711.67 in Chester County, Pennsylvania to tie-in to an 
    existing Transco 16-inch lateral.
        (10) Installation of a pressure control valve and related piping, 
    and a 290 hp nameplate uprating of six existing reciprocating engines 
    (for a total nameplate uprating of 1,740 hp) at Transco's existing 
    Compressor Station 200 located at milepost 1722.24 in Chester County, 
    Pennsylvania.
        Transco estimates that the proposed facilities will cost $117.7 
    million. Transco requests that the Commission grant rolled-in rate 
    treatment of the costs of the SeaBoard facilities in Transco's next 
    Section 4 rate proceeding which becomes effective following the in-
    service date of the Project. It is stated that the rate impact on 
    existing customers of rolling in the costs of the SeaBoard Expansion 
    Project is below the five percent threshold specified in the 
    Commission's Statement of Policy, 71 FERC para. 61,241 (1995), for 
    establishing a presumption in favor of rolled-in rates and the Project 
    will produce significant system-wide operational and financial benefits 
    and will be operated on an integrated basis with its existing 
    facilities.
        To meet the proposed in-service date for the SeaBoard Expansion 
    Project, Transco requests that the Commission issue a preliminary 
    determination approving all aspects of the application other than 
    environmental matters by November 1, 1996, with a final determination 
    and all appropriate certificate authorizations by January 24, 1997.
        Comment date: June 21, 1996, in accordance with Standard Paragraph 
    F at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or make any protest with 
    reference to said filing should on or before the comment date file with 
    the Federal Energy Regulatory Commission, 888 First Street, N.E., 
    Washington, D.C. 20426, a motion to intervene or a protest in 
    accordance with the requirements of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.211 and 385.214) and the Regulations under 
    the Natural Gas Act (18 CFR 157.10). All protests filed with the 
    Commission will be considered by it in determining the appropriate 
    action to be taken but will not serve to make the protestants parties 
    to the proceeding. Any person wishing to become a party to a proceeding 
    or to participate as a party in any hearing therein must file a motion 
    to intervene in accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this filing if no motion to intervene is filed within the time required 
    herein, if the Commission on its own review of the matter finds that a 
    grant of the certificate is required by the public convenience and 
    necessity. If a motion for leave to intervene is timely filed, or if 
    the Commission on its own motion believes that a formal hearing is 
    required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for the applicant to appear or be represented at 
    the hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    the issuance of the instant notice by the Commission, file pursuant to 
    Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion 
    to intervene or notice of intervention and pursuant to Section 157.205 
    of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest 
    to the request. If no protest is filed within the time allowed 
    therefore, the proposed activity shall be deemed to be authorized 
    effective the day after the time allowed for filing a protest. If a 
    protest is filed and not withdrawn within 30 days after the time 
    allowed for filing a protest, the instant request shall be treated as 
    an application for authorization pursuant to Section 7 of the Natural 
    Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-14347 Filed 6-6-96; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
06/07/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-14347
Dates:
July 15, 1996, in accordance with Standard Paragraph G at the end of this notice.
Pages:
29089-29092 (4 pages)
Docket Numbers:
Docket No. CP96-519-000, et al.
PDF File:
96-14347.pdf