98-19199. NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 138 (Monday, July 20, 1998)]
    [Notices]
    [Pages 38822-38823]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-19199]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-651-000]
    
    
    NorAm Gas Transmission Company; Notice of Request Under Blanket 
    Authorization
    
    July 14, 1998.
        Take notice that on July 2, 1998, NorAm Gas Transmission Company 
    (NorAm), 1111 Louisiana, Houston, Texas 77002, filed in Docket No. 
    CP98-651-000 a request pursuant to Sections 157.205, 157.212, and 
    157.216 of the Commission's Regulations under the Natural Gas Act (18 
    CFR 157.205, 157.212, and 157.216) for authorization to upgrade 
    facilities in Oklahoma. NorAm makes such request under its blanket 
    certificate issued in Docket Nos. CP82-384-000 and CP82-384-001 
    pursuant to Section 7 of the Natural Gas Act, all as more fully set 
    forth in the request on file with the Commission and open to public 
    inspection.
        Specifically, NorAm seeks authority to (1) operate under Subpart G 
    of Part
    
    [[Page 38823]]
    
    284 of the Commission's Regulations, measurement facilities constructed 
    under Section 311 of the Natural Gas Policy Act and Subpart B, Part 284 
    of the Commission's Regulations; and (2) abandon obsolete measurement 
    facilities and install upgraded delivery facilities at Delhi, Oklahoma 
    to continue service to Arkla, a division of NorAm Energy Corporation 
    (Arkla).
        NorAm states that pursuant to Section 311, that it upgraded an 
    existing delivery tap located on NorAm's Line 11-2 at pipeline station 
    no. 355+41 in Comanche County, Oklahoma. It is stated that Arkla 
    requested upgraded service and increased deliveries at that location, 
    and that NorAm accordingly installed a Roots rotary 16M meter and two 
    1-inch Fisher regulators at an estimated cost of $600. (It is averred 
    that Arkla fabricated the new meter and regulators and donated those 
    facilities to NorAm at no cost.) NorAm states that it will own and 
    operate those facilities and seeks authority to operate those 
    facilities under Subpart G. NorAm estimates that up to 69,370 
    dekatherms (Dt) will be delivered to that tap annually and 651 Dt on a 
    peak day.
        At Delhi, Oklahoma, NorAm proposes to abandon and junk an American 
    AL 800 meter, one 1-inch Fisher 630 regulator and one 1-inch Reliance 
    1800 regulator located at an existing town border station on NorAm's 
    Line 8 at pipeline station no. 400+62 in Beckham County, Oklahoma. 
    NorAm states that it will install a Roots 11M positive displacement 
    meter and one 1-inch 399 Fisher regulator at an estimated cost of $600. 
    (It is indicated that Arkla will fabricate the new meter and regulator 
    and donate those facilities to NorAm at no cost.) The estimated volumes 
    to be delivered to that tap are approximately 10,409 Dt annually and 
    492 Dt on a peak day.
        NorAm states that the volumes in this request will be within 
    Arkla's certificated entitlements, and that NorAm's tariff does not 
    prohibit the addition of new delivery points. It is further stated that 
    NorAm has sufficient capacity to accomplish the deliveries without 
    detriment or disadvantage to its other customers.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-19199 Filed 7-17-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
07/20/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-19199
Pages:
38822-38823 (2 pages)
Docket Numbers:
Docket No. CP98-651-000
PDF File:
98-19199.pdf