04-13625. Federal Acquisition Regulation; Application of Cost Principles and Procedures and Accounting for Unallowable Costs  

  • Start Preamble

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Final rule.

    SUMMARY:

    The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) have agreed on a final rule amending the Federal Acquisition Regulation (FAR) to revise FAR 31.204, Application of principles and procedures, to improve clarity and structure.

    DATES:

    Effective Date: July 19, 2004.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    The FAR Secretariat at (202) 501-4755 for information pertaining to status or publication schedules. For clarification of content, contact Mr. Edward Loeb, Policy Advisor, at (202) 501-0650. Please cite FAC 2001-24, FAR case 2002-006.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    DoD, GSA, and NASA published a proposed rule in the Federal Register at (68 FR 28108) on May 22, 2003, with request for comments. The rule proposed to amend FAR 31.204, Application of principles and procedures, and FAR 31.201-6, Accounting for unallowable costs. Nine respondents submitted comments; however, no comments related to FAR 31.204. Therefore, the Councils concluded that the proposed rule should be converted to a final rule without changes. Start Printed Page 34242

    The proposed FAR rule also included proposed revisions to FAR 31.201-6, Accounting for unallowable costs. Due to significant changes made as a result of public comments received, the Councils have decided that the proposed revisions to FAR 31.201-6 will be published as a second proposed rule in a Federal Register notice under new FAR case 2004-006.

    This is not a significant regulatory action and, therefore, was not subject to review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    B. Public Comments

    There were no public comments received on section 31.204.

    C. Regulatory Flexibility Act

    The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because most contracts awarded to small entities use simplified acquisition procedures or are awarded on a competitive, fixed-price basis, and do not require application of the cost principles and procedures discussed in this rule. For FY 2003, only 2.4 % of all contract actions were cost contracts awarded to small business.

    D. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply because the changes to the FAR do not impose information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Part 31

    • Government procurement
    End List of Subjects Start Signature

    Dated: June 10, 2004.

    Ralph J. De Stefano,

    Acting Director, Acquisition Policy Division.

    End Signature Start Amendment Part

    Therefore, DoD, GSA, and NASA amend 48 CFR part 31 as set forth below:

    End Amendment Part Start Part

    PART 31—CONTRACT COST PRINCIPLES AND PROCEDURES

    End Part Start Amendment Part

    1. The authority citation for 48 CFR part 31 is revised to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42 U.S.C. 2473(c).

    End Authority Start Amendment Part

    2. Amend section 31.204 in the first sentence of paragraph (a) by removing “shall be allowed” and adding “are allowable” in its place; by revising paragraph (b); and by redesignating paragraph (c) as paragraph (d) and adding a new paragraph (c) to read as follows:

    End Amendment Part
    Application of principles and procedures.
    * * * * *

    (b)(1) For the following subcontract types, costs incurred as reimbursements or payments to a subcontractor are allowable to the extent the reimbursements or payments are for costs incurred by the subcontractor that are consistent with this part:

    (i) Cost-reimbursement.

    (ii) Fixed-price incentive.

    (iii) Price redeterminable (i.e., fixed-price contracts with prospective price redetermination and fixed-ceiling-price contracts with retroactive price redetermination).

    (2) The requirements of paragraph (b)(1) of this section apply to any tier above the first firm-fixed-price subcontract or fixed-price subcontract with economic price adjustment provisions.

    (c) Costs incurred as payments under firm-fixed-price subcontracts or fixed-price subcontracts with economic price adjustment provisions or modifications thereto, for which subcontract cost analysis was performed are allowable if the price was negotiated in accordance with 31.102.

    * * * * *
    End Supplemental Information

    [FR Doc. 04-13625 Filed 6-17-04; 8:45 am]

    BILLING CODE 6820-EP-P

Document Information

Published:
06/18/2004
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
04-13625
Pages:
34241-34242 (2 pages)
Docket Numbers:
FAC 2001-24, FAR Case 2002-006, Item VIII
RINs:
9000-AJ65: FAR Case 2002-006, Application of the Cost Principles and Procedures and Accounting for Unallowable Costs
RIN Links:
https://www.federalregister.gov/regulations/9000-AJ65/far-case-2002-006-application-of-the-cost-principles-and-procedures-and-accounting-for-unallowable-c
Topics:
Government procurement
PDF File:
04-13625.pdf
CFR: (1)
48 CFR 31.204