05-5901. Notice of Issuance of Partial Conditional Exemption; Portland General Electric Company, Trojan Independent Spent Fuel Storage Facility
-
Start Preamble
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Notice of partial conditional exemption.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Christopher M. Regan, Senior Project Manager, Spent Fuel Project Office, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555. Telephone: (301) 415-8500; fax number: (301) 415-8555; e-mail: cmr1@nrc.gov.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
Portland General Electric Company (PGE) is the licensee and holder of License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Facility (Trojan ISFSI). In addition, PGE holds License No. NPF-1, pursuant to 10 CFR part 50, for the Trojan Nuclear Plant. The licensee will complete decommissioning of the Trojan Nuclear Plant and intends to terminate its Part 50 license for the Trojan Nuclear Plant. The Trojan ISFSI contains the spent fuel removed from the Trojan Nuclear Plant.
Currently, the licensee provides financial assurance for the Trojan ISFSI pursuant to 10 CFR 72.30(c)(5), which allows a part 50 license holder to use the financial assurance provisions of part 50 to provide financial assurance for an ISFSI. The licensee maintains an external sinking fund for decommissioning funds pursuant to 10 CFR 50.75(e). However, when its part 50 license is terminated, it will no longer meet the condition of 10 CFR 72.30(c)(5) that allows it to use its existing external sinking fund to provide financial assurance for its ISFSI.
On April 29, 2004, PGE filed a request for NRC approval of a partial exemption from the provision of 10 CFR 72.30(c)(5) that requires an ISFSI licensee to additionally hold a part 50 license in order to use an external sinking fund as the exclusive means of financial assurance for decommissioning costs of an ISFSI.
II. Requested Action
Pursuant to the requirements of 10 CFR 72.7, PGE requested a partial exemption from the financial assurance requirements of 10 CFR 72.30(c)(5). The exemption request was “partial” because it would apply only to the requirement that the ISFSI licensee also hold a Part 50 license to use an external sinking fund as its exclusive method of providing financial assurance for its ISFSI. The licensee will continue to provide financial assurance conforming to the requirements of 10 CFR 50.75(e) and (h), although it reserved the right to change to another method as provided in other sections of 10 CFR 72.30(c). The licensee pointed out that the wording of 10 CFR 72.30(c)(5) allowed an “electric utility” to use an external sinking fund as the exclusive method of providing financial assurance when its part 72 ISFSI license was first issued. However, the rule was amended effective on December 24, 2003, which resulted in the change of the condition from “electric utility” to “a part 50 licensee.” PGE stated that it will remain an electric utility after the termination of its part 50 license, hence it will continue to meet the intent of the rule as originally issued.
III. Discussion
The Commission may grant a specific exemption to the financial assurance requirements of 10 CFR 72.30(c)(5) provided that the requirements of 10 CFR 72.7 are satisfied. The Commission determined that a partial exemption from 10 CFR 72.30(c)(5) meets the Start Printed Page 15370requirements of 10 CFR 72.7, as discussed below:
Specific Exemption Is Authorized by Law
Prior to December 24, 2003, any ISFSI licensee that met the definition of “electric utility” in 10 CFR 50.2 was eligible to use the financial assurance methods of 10 CFR 50.75(e) to provide financial assurance for its ISFSI. As a result, the NRC approved use of an external sinking fund conforming to the requirement of 10 CFR 50.75(e)(1)(ii)(A) as financial assurance for the Trojan ISFSI pursuant to 10 CFR 72.30(c)(5).
The amendment to 10 CFR 72.30(c)(5) that became effective December 24, 2003, was incidental to the primary changes in Part 50 issued at the same time with regard to reactor decommissioning trust funds. The amendment to 10 CFR 72.30(c)(5) was in response to a comment that suggested the change to maintain consistency between parts 72 and 50, but did not change the basis of the regulations.
The basis of 10 CFR 50.75(e)(1)(ii)(A) is that a licensee that recovers decommissioning costs through rates established through “cost of service” or similar rate-making authority may use an external sinking fund as its exclusive means of financial assurance. A licensee that is a public utility is presumed to meet that basis. Because PGE will remain a public utility after termination of its part 50 license, it will continue to meet the basis for allowing a part 72 licensee to provide financial assurance using the methods of part 50. Therefore, the partial exemption from part 72 is authorized by law.
Specific Exemption Will Not Present an Undue Risk to the Public Health and Safety
The specific exemption requested is administrative in nature. The exemption does not have any reasonable potential to (1) foreclose release of the Trojan ISFSI site for unrestricted use; (2) result in significant environmental impacts not previously reviewed; or (3) result in there no longer being reasonable assurance that adequate funds will be available for decommissioning. The exemption will allow use of a financial assurance method currently in use that has been approved by the NRC. Therefore, the partial exemption will not present an undue risk to the public health.
Specific Exemption Will Not Endanger the Common Defense and Security
The partial exemption is administrative in nature and does not involve information of activities that could potentially impact the common defense and security of the United States. Therefore, partial exemption will not endanger the common defense and security.
Specific Exemption Is Otherwise in the Public Interest
PGE's 2003 Annual Financial Statement (Form 10-K, submitted to the U.S. Securities and Exchange Commission (SEC) on March 19, 2004) stated that PGE will collect $14 million annually, until 2011, from its customers to pay for decommissioning. This includes funding for radiological and non-radiological decontamination as well as on-site spent nuclear fuel storage. Those collections will occur whether or not the exemption is granted. However, if the exemption is not granted, PGE will incur higher costs due to the expense of providing a second independent financial assurance instrument, which would lead to unnecessary additional costs. Therefore, the exemption is in the public interest.
Financial Ability of PGE To Fund the ISFSI Decommissioning Cost
The Trojan ISFSI decommissioning cost estimate was $7.9 million in 1997. Adjusting for inflation to 2004 would increase the cost to about $10 million. In order to assess the ability of PGE to finance that cost, the staff reviewed PGE's 2003 Form 10-K. The financial statements show that PGE possesses $3.37 billion in assets and earns $1.7 billion annually in revenues. The financial report stated that PGE maintained a strong financial position with stable cash flow, and will receive $14 million per year through 2011 for decommissioning costs. The cost of decommissioning the Trojan ISFSI appears well within the licensee's financial ability.
At the time of filing its exemption request, PGE was a wholly owned subsidiary of Enron Corporation. The staff determined that Enron's bankruptcy will not adversely affect PGE's ability to fund decommissioning of its Trojan ISFSI. Although Enron filed for bankruptcy protection, PGE did not. Regulatory “ring-fencing” effectively insulated PGE and its customers from the effects of Enron's bankruptcy. (Ring fencing is a state public utility board's regulatory strategy that prevents a utility's assets from being pledged as security for a parent company's obligations.) PGE's Quarterly Report, Form 10-Q, submitted to the SEC on November 5, 2004, states on page 41:
PGE, as a separate corporation, owns or leases the assets used in its business and PGE's management, separate from Enron, is responsible for PGE's day-to-day operations. PGE maintains its own cash management system and finances itself separately from Enron, on both a short- and long-term basis. Neither PGE nor Enron have guaranteed the obligations of the other and there are no loans between them. Under Oregon law and specific conditions imposed on Enron and PGE by the Oregon Public Utilities Commission (OPUC) in connection with Enron's acquisition of PGE in the merger of Enron and Portland General Corporation in 1997, Enron's access to PGE cash or utility assets (through dividends or otherwise) is limited.
Therefore, PGE's assets will be available to provide funding for decommissioning if it continues as an Enron subsidiary. However, Enron entered into an agreement with Oregon Electric Utility Company, LLC, to sell all issued and outstanding PGE stock to Oregon Electric. In the event the sale is consummated, the Enron bankruptcy will be of no further concern.
IV. Conclusion
The Commission determined that the specific exemption to the financial assurance requirements of 10 CFR 72.30(c)(5) is authorized by law and will not endanger life or property, or the common defense and security and is otherwise in the public interest.
In connection with the issuance of the exemption, an Environmental Assessment and Finding of No Significant Impact was noticed in the Federal Register on March 17, 2005 (70 FR 13052).
Therefore, the Commission grants a partial exemption from the requirement of 10 CFR 72.30(c)(5) that the licensee must hold a part 50 license in order to provide financial assurance using the methods of 10 CFR 50.75(e) and (h); however, the exemption is granted subject to the following two conditions:
1. The exemption shall not become effective until the licensee submits, within 30 days of the issuance of this grant of exemption, documentation adequate to demonstrate that funding for the Trojan ISFSI decommissioning has been approved for recovery in rates by a rate making authority; and
2. The exemption shall cease to be effective in the event that funds remaining to be placed into the Trojan ISFSI decommissioning external sinking fund are no longer approved for recovery in rates by a competent rate regulating authority.
This exemption is effective upon satisfaction of Condition 1 above, and shall cease being effective in the event Condition 2 above is triggered.
Start Further InfoFurther Information:
Supporting documentation, with respect to this exemption request, is available for Start Printed Page 15371inspection at NRC's Public Electronic Reading Room at http://www.nrc.gov/reading-rm/ADAMS.html. A copy of the PGE request for NRC approval of a partial exemption from the provision of 10 CFR 72.30(c)(5), dated April 29, 2004, can be found at this site using the Agencywide Documents Access and Management System (ADAMS) accession No. ML041260470. Any questions should be referred to Christopher M. Regan, Spent Fuel Project Office, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555, Mailstop O 13D13, telephone (301) 415-8500, fax (301) 415-8555.
Start SignatureDated at Rockville, Maryland this 17th day of March, 2005.
For the Nuclear Regulatory Commission.
Christopher M. Regan,
Senior Project Manager, Licensing Section, Spent Fuel Project Office, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 05-5901 Filed 3-24-05; 8:45 am]
BILLING CODE 7590-01-P
Document Information
- Published:
- 03/25/2005
- Department:
- Nuclear Regulatory Commission
- Entry Type:
- Notice
- Action:
- Notice of partial conditional exemption.
- Document Number:
- 05-5901
- Pages:
- 15369-15371 (3 pages)
- Docket Numbers:
- Docket No. 72-17
- PDF File:
- 05-5901.pdf