2011-6198. BOST3 Hydroelectric Company, LLC (BOST3); Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests  

  • Start Preamble

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: Original Major License.

    b. Project No.: P-12756-003.

    c. Date filed: July 26, 2010.

    d . Applicant: BOST3 Hydroelectric Company, LLC (BOST3).

    e. Name of Project: Red River Lock & Dam No. 3 Hydroelectric Project.

    f. Location: The proposed project would be located at the existing Army Corps of Engineer's (Corps) Red River Lock & Dam No. 3 on the Red River, in Natchitoches Parish near the City of Colfax, Louisiana.

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).

    h. Applicant Contact: Mr. Douglas A. Spalding, BOST3 Hydroelectric Company, LLC, 8441 Wayzata Blvd., Suite 101, Golden Valley, MN 55426; (952) 544-8133.

    i. FERC Contact: Jeanne Edwards (202) 502-6181, or by e-mail at Jeanne.edwards@ferc.gov.

    j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice.

    All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site http://www.ferc.gov/​docs-filing/​efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/​docs-filing/​ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, or toll free at 1-866-208-3676, or for TTY, (202) 502-8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    The Commission's Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted for filing, but is not ready for environmental analysis at this time.

    l. The proposed project would utilize the Corps' existing Red River Lock and Dam No. 3, and be operated consistent with the Corps' current operating manual. The proposed project consists of: (1) An excavated headrace channel to convey water from the upstream Pool No. 3 of the Red River into the powerhouse; (2) an excavated tailrace channel to discharge water from the powerhouse to the downstream Pool No. 2 of the Red River; (3) a 301-foot-long by 90-foot-wide concrete powerhouse located on the right (west) abutment of the Corps' Lock and Dam No. 3; (4) one 36.2-megawatt (MW) horizontal Kaplan bulb turbine/generator unit; (5) one 2,300-foot-long, 13.2-kilovolt (kV) overhead transmission line which crosses the river and connects to a Central Louisiana Electric Company substation located on the opposite side of the river; and (6) appurtenant facilities. The proposed project would generate about 172,779 megawatt-hours (MWh) annually, which would be sold to a local utility.

    m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.Start Printed Page 14654

    n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice.

    A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice.

    Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

    When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, or prescriptions.

    All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE,” “NOTICE OF INTENT TO FILE COMPETING APPLICATION,” or “COMPETING APPLICATION;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

    Start Signature

    Dated: March 10, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2011-6198 Filed 3-16-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
03/17/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-6198
Pages:
14653-14654 (2 pages)
Docket Numbers:
Project No. 12756-003
PDF File:
2011-6198.pdf