2015-24196. Kerr-Philpott System  

  • Start Preamble

    AGENCY:

    Southeastern Power Administration, (Southeastern), Department of Energy.

    ACTION:

    Notice of interim approval.

    SUMMARY:

    The Deputy Secretary, Department of Energy, confirmed and approved, on an interim basis new rate schedules VA-1-C, VA-2-C, VA-3-C, VA-4-C, DEP-1-C, DEP-2-C, DEP-3-C, DEP-4-C, AP-1-C, AP-2-C, AP-3-C, AP-4-C, NC-1-C, and Replacement-2-B. These rate schedules are applicable to Southeastern power sold to existing preference customers in the Virginia and North Carolina service area. The rate schedules are approved on an interim basis through September 30, 2020, and are subject to confirmation and approval by the Federal Energy Regulatory Commission (FERC) on a final basis.

    DATES:

    The rates are effective October 1, 2015.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Virgil G. Hobbs III, Assistant Administrator, Finance and Marketing, Southeastern Power Administration, Department of Energy, 1166 Athens Tech Road, Elberton, Georgia 30635-4578, (706) 213-3800.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    The Federal Energy Regulatory Commission, by Order issued March 11, 2011, in Docket No. EF10-8-000 (134 FERC 62,233), confirmed and approved Wholesale Power Rate Schedules VA-1-B, VA-2-B, VA-3-B, VA-4-B, CP&L-1-B, CP&L-2-B, CP&L-3-B, CP&L-4-B, AP-1-B, AP-2-B, AP-3-B, AP-4-B, NC-1-B, and Replacement-2-A through September 30, 2015. This order replaces these rate schedules on an interim basis, subject to final approval by FERC.

    Start Signature

    Dated: September 16, 2015.

    Elizabeth Sherwood-Randall,

    Deputy Secretary of Energy.

    End Signature

    Department of Energy

    Deputy Secretary

    In the Matter of: Southeastern Power Administration), Kerr-Philpott System Power Rates), Rate Order No. SEPA-58

    Order Confirming and Approving Power Rates on an Interim Basis

    Pursuant to Sections 302(a) of the Department of Energy Organization Act, Public Law 95-91, the functions of the Secretary of the Interior and the Federal Power Commission under Section 5 of the Flood Control Act of 1944, 16 U.S.C. 825s, relating to the Southeastern Power Administration (Southeastern), were transferred to and vested in the Secretary of Energy. By Delegation Order No. 00-037.00A, effective December 6, 2001, the Secretary of Energy delegated to Southeastern's Administrator the authority to develop power and transmission rates, to the Deputy Secretary of Energy the authority to confirm, approve, and place in effect such rates on interim basis, and to the Federal Energy Regulatory Commission (FERC) the authority to confirm, approve, and place into effect on a final basis or to disapprove rates developed by the Administrator under the delegation. This rate is issued by the Deputy Secretary pursuant to that delegation order.

    Background

    Power from the Kerr-Philpott Projects is presently sold under Wholesale Start Printed Page 57354Power Rate Schedules VA-1-B, VA-2-B, VA-3-B, VA-4-B, CP&L-1-B, CP&L-2-B, CP&L-3-B, CP&L-4-B, AP-1-B, AP-2-B, AP-3-B, AP-4-B, NC-1-B, and Replacement-2-A. These rate schedules were approved by the FERC on March 11, 2011, for a period ending September 30, 2015 (134 FERC 62,233).

    Public Notice and Comment

    Notice of a proposed rate adjustment for the Kerr-Philpott System was published in the Federal Register (80 FR 12819) on March 11, 2015. The notice advised interested parties that a public information and comment forum would be held in Boydton, Virginia on April 21, 2015. Written comments were due on or before June 9, 2015. The proposed rate adjustment was a reduction of about six percent (6%).

    Subsequent to the Public Information and Comment Forum on April 21, Southeastern discovered an error due to omissions in the repayment study used to develop the proposed rate schedules. Two accounting lines were omitted from the estimated Corps O&M expenses included in the study. The accounting lines were Work Category Code 602, Operation for Flood Damage Reduction, and Work Category Code 612, Maintenance for Flood Damage Reduction. On June 1, 2015, Southeastern sent a letter to all Kerr-Philpott customers notifying them of the error and notifying them Southeastern intended to add the omitted accounting lines and correct the error in the rate schedules Southeastern would recommend to the Deputy Secretary. After these corrections, the proposed rate is an increase of about 2.2 percent.

    Southeastern received comments from one source, the Southeast Federal Power Customers, Inc., as a result of the above notifications. The comments and Southeastern's response are below.

    Comment: The SeFPC questions whether the expenses in accounts WCC 602 and 612 should properly be assigned to hydropower as a joint expense. Given the Congressional Mandate to provide flood control at the Kerr and Philpott projects, the assignment of these costs appears to be arbitrary, capricious, and not consistent with the authorizing statutes. The SeFPC would ask SEPA to review the inclusion of these costs and work with Corps representatives to remove such expenses as joint expense for purpose of the proposed rate. Failure to take this action would impose over $10 million in additional cost for the hydropower customers over the five year study period in the repayment study which should properly be borne by the flood control purpose.

    The referenced Work Category Codes 602 and 612 contain operation and maintenance expenses associated with flood risk management. The Corps has taken the position the John H. Kerr and Philpott final cost allocations state that the only specific costs at these reservoirs are Power and Recreation, and that as a result, the Corps cannot charge costs to the flood control purpose at these projects.

    The $10 million assigned to hydropower and disputed by SeFPC include the operations, maintenance and readiness of equipment associated with spillways, sluices, pumping plants and earthen dams. The Corps has included these costs in the O&M expenses included in the financial statements provided to Southeastern for the John H. Kerr and Philpott projects. SeFPC has raised legitimate questions about the nature and assignment of WCC s 602 and 612. Further study of this issue is necessary. Southeastern will continue to discuss with the Corps the appropriateness of assigning these costs solely to hydropower.

    Southeastern and the Corps have discussed the need for a new authorized purpose allocation study and agreed to jointly fund the effort. Once completed, Southeastern and the Corps will work together to determine whether costs in these accounts should be allocated to purposes other than Power and Recreation. A reallocation could significantly reduce the proportion of charges assigned to Southeastern's power customers and ensure that costs are being assigned to appropriate cost-causers.

    Discussion

    System Repayment

    An examination of Southeastern's revised system power repayment study, prepared in July 2015, for the Kerr-Philpott System shows that with the proposed rates, all system power costs are paid within the appropriate repayment period required by existing law and DOE Procedure RA 6120.2. The Administrator of Southeastern Power Administration has certified that the rates are consistent with applicable law and that they are the lowest possible rates to customers consistent with sound business principles, pursuant to section 5 of the Flood Control Act (16 U.S.C.A.835(s)).

    Environmental Impact

    Southeastern has reviewed the possible environmental impacts of the rate adjustment under consideration and has concluded that, because the adjusted rates would not significantly affect the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 (42 U.S.C.A 4332), the proposed action is not a major Federal action for which preparation of an Environmental Impact Statement is required.

    Availability of Information

    Information regarding these rates, including studies and other supporting materials and transcripts of the public information and comment forum, is available for public review in the offices of Southeastern Power Administration, 1166 Athens Tech Road, Elberton, Georgia 30635, and in the Power Marketing Liaison Office, James Forrestal Building, 1000 Independence Avenue SW., Washington, DC 20585.

    Order

    In view of the foregoing and pursuant to the authority delegated to me by the Secretary of Energy, I hereby confirm and approve on an interim basis, effective October 1, 2015, attached Wholesale Power Rate Schedules VA-1-C, VA-2-C, VA-3-C, VA-4-C, DEP-1-C, DEP-2-C, DEP-3-C, DEP-4-C, AP-1-C, AP-2-C, AP-3-C, AP-4-C, NC-1-C, and Replacement-2-B. The Rate Schedules shall remain in effect on an interim basis through September 30, 2020, unless such period is extended or until the FERC confirms and approves them or substitutes Rate Schedules on a final basis.

    Dated: September 16, 2015.

    Elizabeth Sherwood-Randall

    Deputy Secretary of Energy

    Wholesale Power Rate Schedule VA-1-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia and North Carolina to whom power may be transmitted and scheduled pursuant to contracts between the Government, Virginia Electric and Power Company (hereinafter called the Company), the Company's Transmission Operator, currently PJM Interconnection LLC (hereinafter called PJM), and the Customer. This rate schedule is applicable to customers receiving power from the Government on an arrangement where the Company schedules the power and provides the Customer a credit on their bill for Government power. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability: Start Printed Page 57355

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    2016$2,730,000$3,220,000
    2017$2,420,000$5,640,000
    2018$1,910,000$7,550,000
    2019$1,910,000$9,460,000
    2020$2,010,000$11,470,000
    2021$2,110,000$13,580,000
    2022$2,190,000$15,770,000
    2023$2,290,000$18,060,000
    2024$2,400,000$20,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and any ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company or PJM. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $0.775 per kilowatt of total contract demand per month estimated as of April 2015, is presented for illustrative purposes.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charge:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts) in the month incurred.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy Start Printed Page 57356each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule VA-2-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia and North Carolina to whom power may be transmitted pursuant to contracts between the Government, Virginia Electric and Power Company (hereinafter called the Company), the Company's Transmission Operator, currently PJM Interconnection LLC (hereinafter called PJM), and the Customer. The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is responsible for providing a scheduling arrangement with the Government. The Government is responsible for arranging transmission with the Company and PJM. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and any ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company or PJM. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $0.775 per kilowatt of total contract demand per month estimated as of April 2015, is presented for illustrative purposes.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and ancillary services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may Start Printed Page 57357charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charge:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts) in the month incurred.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule VA-3-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia and North Carolina to whom power may be scheduled pursuant to contracts between the Government, Virginia Electric and Power Company (hereinafter called the Company), the Company's Transmission Operator, currently PJM Interconnection LLC (hereinafter called PJM), and the Customer. The Government is responsible for providing the scheduling. The Customer is responsible for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base Start Printed Page 57358capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for Transmission and Ancillary Services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company or PJM. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charge:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts) in the month incurred.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the Federal Energy Regulatory Commission, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule VA-4-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia and North Carolina served through the transmission facilities of Virginia Electric and Power Company (hereinafter called the Company) and PJM Interconnection LLC (hereinafter called PJM). The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    Start Printed Page 57359
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company or PJM. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charge:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts) in the month incurred.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule DEP-1-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in North Carolina and South Carolina to whom power may be transmitted and scheduled pursuant to contracts between the Government and Duke Energy Progress (formerly known as Carolina Power & Light Company and hereinafter called the Company) and the Customer. This rate schedule is applicable to customers receiving power from the Government on an arrangement where the Company schedules the power and provides the Customer a credit on their bill for Government power. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability: Start Printed Page 57360

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $1.546 per kilowatt of total contract demand per month as of April 2015, is presented for illustrative purposes.

    The initial transmission charge will be the Customer's ratable share of the transmission and distribution charges paid by the Government. The rate is subject to periodic adjustment and will be computed in accordance with the terms of the Government-Company contract.

    Proceedings before FERC involving the Company's Open Access Transmission Tariff (OATT) or the distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission, in accordance with the Government-Company contract, is six (6) per cent. This loss factor will be governed by the terms of the Government-Company contract.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.Start Printed Page 57361

    Wholesale Power Rate Schedule DEP-2-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in North Carolina and South Carolina to whom power may be transmitted pursuant to contracts between the Government and Duke Energy Progress (formerly known as Carolina Power & Light Company and hereinafter called the Company) and the Customer. The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is responsible for providing a scheduling arrangement with the Government. The Government is responsible for arranging transmission with the Company. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $1.546 per kilowatt of total contract demand per month as of April 2015, is presented for illustrative purposes.

    The initial transmission charge will be the Customer's ratable share of the transmission and distribution charges paid by the Government. The rate is subject to periodic adjustment and will be computed in accordance with the terms of the Government-Company contract.

    Proceedings before FERC involving the Company's Open Access Transmission Tariff (OATT) or the distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.Start Printed Page 57362

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission, in accordance with the Government-Company contract, is six (6) per cent. This loss factor will be governed by the terms of the Government-Company contract.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule DEP-3-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in North Carolina and South Carolina to whom power may be scheduled pursuant to contracts between the Government and Duke Energy Progress (formerly known as Carolina Power & Light Company and hereinafter called the Company) and the Customer. The Government is responsible for providing the scheduling. The Customer is responsible for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Proceedings before FERC involving the Company's Open Access Transmission Tariff (OATT) or the distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission and distribution charges paid by the Government in behalf of the Customer.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or Start Printed Page 57363an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission, in accordance with the Government-Company contract, is six (6) per cent. This loss factor will be governed by the terms of the Government-Company contract.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule DEP-4-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in North Carolina and South Carolina served through the transmission facilities of Duke Energy Progress (formerly known as Carolina Power & Light Company and hereinafter called the Company). The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or Start Printed Page 57364an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission, in accordance with the Government-Company contract, is six (6) per cent. This loss factor will be governed by the terms of the Government-Company contract.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule AP-1-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia to whom power may be transmitted and scheduled pursuant to contracts between the Government, American Electric Power Service Corporation (hereinafter called the Company), the Company's Transmission Operator, currently PJM Interconnection LLC (hereinafter called PJM), and the Customer. This rate schedule is applicable to customers receiving power from the Government on an arrangement where the Company schedules the power and provides the Customer a credit on their bill for Government power. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $0.775 per kilowatt of total contract demand per month estimated as of April 2015, is a presented for illustrative purposes.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are Start Printed Page 57365governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charge:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts).

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule AP-2-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia to whom power may be transmitted pursuant to contracts between the Government, American Electric Power Service Corporation (hereinafter called the Company), the Company's Transmission Operator, currently PJM Interconnection LLC (hereinafter called PJM), and the Customer. The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is responsible for providing a scheduling arrangement with the Government. The Government is responsible for arranging transmission with the Company. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Company's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table Start Printed Page 57366above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Transmission:

    $0.775 per kilowatt of total contract demand per month estimated as of April 2015, is presented for illustrative purposes.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charges:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts).

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the Federal Energy Regulatory Commission, pursuant to application by American Electric Power Service Corporation under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule AP-3-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia to whom power may be scheduled pursuant to contracts between the Government, American Electric Power Service Corporation (hereinafter called the Company), PJM Interconnection LLC (hereinafter called PJM), and the Customer. The Government is responsible for providing the scheduling. The Customer is responsible for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:Start Printed Page 57367

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charges:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts).

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule AP-4-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia served through the facilities of American Electric Power Service Corporation (hereinafter called the Company) and PJM Interconnection LLC (hereinafter called PJM). The Customer has chosen to self-schedule and does not receive Government power under an arrangement where the Company schedules the power and provides a credit on the Customer's bill for Government power. The Customer is Start Printed Page 57368responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects (hereinafter called the Projects) and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the Projects.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every $100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for Transmission and Ancillary Services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Company. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of the Company's rate.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Company's or PJM's OATT.

    Capacity Performance Non-Performance Charges:

    Requirements of the PJM capacity performance market may lead to non-performance charges to Southeastern. These non-performance charges, if incurred, will be allocated to the capacity delivered in PJM (currently 120,100 kilowatts).

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will Start Printed Page 57369purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Company (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Company's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the Federal Energy Regulatory Commission, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule NC-1-C

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in Virginia and North Carolina to whom power may be transmitted pursuant to a contract between the Government and Virginia Electric and Power Company (hereinafter called the Virginia Power) and PJM Interconnection LLC (hereinafter called PJM), scheduled pursuant to a contract between the Government and Duke Energy Progress (formerly known as Carolina Power & Light and hereinafter called DEP), and billed pursuant to contracts between the Government and the Customer. Nothing in this rate schedule shall preclude modifications to the aforementioned contracts to allow an eligible customer to elect service under another rate schedule.

    Applicability:

    This rate schedule shall be applicable to the sale at wholesale of power and accompanying energy generated at the John H. Kerr and Philpott Projects and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The electric capacity and energy supplied hereunder will be delivered at the delivery points of the Customer on the Virginia Power's transmission and distribution system.

    Monthly Rate:

    The initial base monthly rate for capacity, energy, and generation services provided under this rate schedule for the period specified shall be:

    Initial Base Capacity Charge:

    $4.40 per kilowatt of total contract demand per month.

    Initial Base Energy Charge:

    17.80 mills per kilowatt-hour.

    The rates are based on a repayment study that projects that the Kerr-Philpott System will produce the following net revenue available for repayment by fiscal year and cumulative net revenue available for repayment by fiscal year:

    Fiscal yearEstimated annual net revenue available for repaymentCumulative net revenue available for repayment
    2015$490,000$490,000
    20162,730,0003,220,000
    20172,420,0005,640,000
    20181,910,0007,550,000
    20191,910,0009,460,000
    20202,010,00011,470,000
    20212,110,00013,580,000
    20222,190,00015,770,000
    20232,290,00018,060,000
    20242,400,00020,460,000

    The rates include a true-up of the capacity and energy rates based on the variance of the actual cumulative net revenue available for repayment from the planned cumulative net revenue available for repayment in the table above. For every 100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. For every $100,000 of over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and reduce the base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt per hour, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to the customers of the amount of the true-up to the capacity and energy rates by February 1 of the next fiscal year.

    Additional rates for transmission and ancillary services provided under this rate schedule shall be the rates charged Southeastern Power Administration by the Virginia Power and DEP. Future adjustments to these rates will become effective upon acceptance for filing by the Federal Energy Regulatory Commission (FERC) of Virginia Power's or DEP's rate.

    Transmission:

    $0.775 per kilowatt of total contract demand per month estimated as of April 2015, is presented for illustrative purposes.

    Ancillary Services:

    0.34 mills per kilowatt-hour of energy estimated as of April 2015, is presented for illustrative purposes.

    The initial charge for transmission and Ancillary Services will be the Customer's ratable share of the charges for transmission, distribution, and ancillary services paid by the Government. The charges for transmission and ancillary services are governed by and subject to refund based upon the determination in proceedings before the FERC involving the Company's or PJM's Open Access Transmission Tariff (OATT).

    Proceedings before FERC involving the OATT or the Distribution charge may result in the separation of charges currently included in the transmission rate. In this event, the Government may charge the Customer for any and all separate transmission, ancillary services, and distribution charges paid Start Printed Page 57370by the Government in behalf of the Customer. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Tandem Transmission Charge:

    $0.42 per kilowatt of total contract demand per month, as an estimated cost as of April 2015.

    The tandem transmission charge will recover the cost of transmitting power from a project to the border of another transmitting system. This rate will be a formulary rate based on the cost to the Government for transmission of power from the Philpott project to the border of the Virginia Electric and Power Company System and the cost to the Government for transmission of power from the John H. Kerr Project to the border of the Duke Energy Progress System. These charges could be recovered through a capacity charge or an energy charge, as determined by the Government.

    Transmission and Ancillary Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving the Virginian Power or PJM's OATT.

    Transmission, System Control, Reactive, and Regulation Services:

    The charges for transmission and ancillary services shall be governed by and subject to refund based upon the determination in the proceeding involving Virginia Power's, DEP's, or PJM's OATT.

    Contract Demand:

    The contract demand is the amount of capacity in kilowatts stated in the contract which the Government is obligated to supply and the Customer is entitled to receive.

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to Virginia Power (less applicable losses). The Customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Virginia Power's system. The applicable energy loss factor for transmission is specified in the OATT.

    These losses shall be effective until modified by the FERC, pursuant to application by the Company or PJM under Section 205 of the Federal Power Act or Southeastern Power Administration under Section 206 of the Federal Power Act or otherwise.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    Wholesale Power Rate Schedule Replacement-2-B

    Availability:

    This rate schedule shall be available to public bodies and cooperatives (any one of whom is hereinafter called the Customer) in North Carolina and Virginia to whom power is provided pursuant to contracts between the Government and the customer from the John H. Kerr and Philpott Projects (or Kerr-Philpott System).

    Applicability:

    This rate schedule shall be applicable to the sale of wholesale energy purchased to meet contract minimum energy and sold under appropriate contracts between the Government and the Customer.

    Character of Service:

    The energy supplied hereunder will be delivered at the delivery points provided for under appropriate contracts between the Government and the Customer.

    Monthly Charge:

    The customer will pay its ratable share of Southeastern's monthly cost for replacement energy. The ratable share will be the cost allocation factor for the customer listed in the table below times Southeastern's monthly cost for replacement energy purchased for the Kerr-Philpott System, rounded to the nearest $0.01.

    Contract No. 89-00-1501-CustomerCapacity allocationAverage energyCost allocation factor
    1230Albemarle EMC2,5936,950,7071.565921%
    1221B-A-R-C EC3,74010,060,4722.266518%
    853Brunswick EMC3,51510,468,6862.358485%
    854Carteret-Craven EMC2,6797,978,8361.797548%
    869Carteret-Craven EMC5642,2810.009525%
    855Central EMC1,2393,690,1000.831341%
    1220Central Virginia EC7,95621,534,9604.851599%
    1203City of Bedford1,200906,1660.204150%
    1204City of Danville5,6004,228,7750.952698%
    895City of Elizabeth City2,0731,565,2050.352624%
    1215City of Franklin1,003754,3590.169949%
    878City of Kinston1,4661,106,8930.249371%
    880City of Laurinburg415313,3430.070593%
    881City of Lumberton895675,7640.152242%
    1205City of Martinsville1,6001,208,2220.272200%
    882City of New Bern1,204909,0720.204804%
    1206City of Radford1,300981,5750.221138%
    885City of Rocky Mount2,5381,916,3000.431722%
    1208City of Salem2,2001,661,1270.374234%
    892City of Washington2,7032,040,8820.459789%
    889City of Wilson2,9502,227,3770.501805%
    1222Community EC4,23011,394,4662.567053%
    1211Craig-Botetourt EC1,6924,575,8161.030883%
    1231Edgecombe-Martin County EMC4,15511,275,5472.540262%
    875Fayetteville Public Works Commission5,4314,100,6400.923831%
    856Four County EMC4,19812,502,8572.816762%
    891Greenville Utilities Commission7,5345,688,4961.281558%
    857Halifax EMC5851,742,2990.392522%
    1232Halifax EMC2,0215,478,3081.234205%
    1216Harrisonburg Electric Commission2,6912,050,3600.461924%
    858Jones-Onslow EMC5,18415,439,4503.478345%
    859Lumbee River EMC3,72911,106,0402.502074%
    Start Printed Page 57371
    1223Mecklenburg EMC11,34430,806,1626.940303%
    1224Northern Neck EC3,94410,572,2782.381823%
    1225Northern Virginia EC3,2688,875,3411.999521%
    860Pee Dee EMC2,9688,839,5621.991460%
    861Piedmont EMC1,0863,234,5400.728708%
    862Pitt & Greene EMC1,5804,705,6971.060144%
    1226Prince George EC2,5306,781,9131.527893%
    863Randolph EMC3,60810,745,6662.420885%
    1227Rappahannock EC22,42760,450,62413.618889%
    1233Roanoke EMC5,52814,904,4033.357805%
    1228Shenandoah Valley EMC9,93826,943,5206.070091%
    864South River EMC6,11918,224,1504.105709%
    1229Southside EC14,57539,381,0178.872128%
    865Tideland EMC6802,025,2360.456264%
    1234Tideland EMC2,4186,554,0501.476558%
    870Town of Apex145109,4820.024665%
    871Town of Ayden208157,0490.035381%
    893Town of Belhaven182137,4180.030959%
    872Town of Benson12090,6050.020412%
    1212Town of Blackstone389292,5680.065912%
    873Town of Clayton161121,5620.027387%
    1213Town of Culpepper391297,9160.067117%
    894Town of Edenton775585,1590.131830%
    1214Town of Elkton171128,6090.028974%
    1218Town of Enfield259194,8100.043889%
    874Town of Farmville237178,9460.040315%
    876Town of Fremont6045,3030.010206%
    896Town of Hamilton4030,2020.006804%
    897Town of Hertford203153,2740.034531%
    898Town of Hobgood4634,7320.007825%
    877Town of Hookerton3022,6510.005103%
    879Town of La Grange9370,2190.015820%
    868Town of Louisburg8572,552,4520.575041%
    883Town of Pikeville4030,2020.006804%
    884Town of Red Springs11788,3400.019902%
    1207Town of Richlands500377,5690.085062%
    899Town of Robersonville232175,1700.039464%
    900Town of Scotland Neck304229,5330.051711%
    886Town of Selma183138,1730.031129%
    887Town of Smithfield378285,4070.064299%
    901Town of Tarboro2,1451,619,5680.364872%
    888Town of Wake Forest149112,5010.025345%
    1217Town of Wakefield10679,7230.017961%
    1219Town of Windsor331248,9460.056085%
    866Tri-County EMC3,0969,220,7822.077345%
    867Wake EMC2,1646,445,0171.451994%
    Total196,500443,873,428

    Energy to be Furnished by the Government:

    The Government will sell to the Customer and the Customer will purchase from the Government energy each billing month equivalent to a percentage specified by contract of the energy made available to the Facilitator (less any losses required by the Facilitator). The customer's contract demand and accompanying energy will be allocated proportionately to its individual delivery points served from the Facilitator's system.

    Billing Month:

    The billing month for power sold under this schedule shall end at 12:00 midnight on the last day of each calendar month.

    End Supplemental Information

    [FR Doc. 2015-24196 Filed 9-22-15; 8:45 am]

    BILLING CODE 6450-01-P

Document Information

Effective Date:
10/1/2015
Published:
09/23/2015
Department:
Southeastern Power Administration
Entry Type:
Notice
Action:
Notice of interim approval.
Document Number:
2015-24196
Dates:
The rates are effective October 1, 2015.
Pages:
57353-57371 (19 pages)
PDF File:
2015-24196.pdf