§ 603.1100 - Contracting officer's post-award responsibilities.
-
§ 603.1100 Contracting officer's post-award responsibilities.
Generally, the contracting officer's post-award responsibilities are the same responsibilities as those for any cooperative agreement. Responsibilities for a TIA include:
(a) Participating as the business partner to the DOE program official to ensure the Government's substantial involvement in the RD&D project. This may involve attendance with program officials at kickoff meetings or post-award conferences with recipients. It also may involve attendance at the consortium management's periodic meetings to review technical progress, financial status, and future program plans.
(b) Tracking and processing of reports required by the award terms and conditions, including periodic business status reports, programmatic progress reports, and patent reports.
(c) Handling payment requests and related matters. For a TIA using advance payments, that includes reviews of progress to verify that there is continued justification for advancing funds, as discussed in § 603.1105(b). For a TIA using milestone payments, it includes making any needed adjustments in future milestone payment amounts, as discussed in § 603.1105(c).
(d) Making continuation awards for subsequent budget periods, if the agreement includes separate budget periods. See 10 CFR 600.26(b). Any continuation award is contingent on availability of funds, satisfactory progress towards meeting the performance goals and milestones, submittal of required reports, and compliance with the terms and conditions of the award.
(e) Coordinating audit requests and reviewing audit reports for both single audits of participants' systems and any award-specific audits that may be needed, as discussed in §§ 603.1115 and 603.1120.
(f) Responding, after coordination with program officials and intellectual property counsel, to recipient requests for permission to assign or license intellectual property to entities that do not agree to manufacture substantially in the United States, as described in § 603.875(b). Before granting approval for any technology, the contracting officer must secure assurance that any such assignment is consistent with license rights for Government use of the technology, and that other conditions for any such transfer are met.