Table 1 to Subpart OOO of Part 60 - Exceptions to Applicability of Subpart A to Subpart OOO  


Latest version.
  • Table 1 to Subpart OOO of Part 60 - Exceptions to Applicability of Subpart A to Subpart OOO

    Subpart A reference Applies to
    subpart OOO
    Explanation
    60.4, Address Yes Except in § 60.4(a) and (b) submittals need not be submitted to both the EPA Region and delegated State authority (§ 60.676(k)).
    60.7, Notification and recordkeeping Yes Except in (a)(1) notification of the date construction or reconstruction commenced (§ 60.676(h)).
    Also, except in (a)(6) performance tests involving only Method 9 (40 CFR part 60, appendix A-4) require a 7-day advance notification instead of 30 days (§ 60.675(g)).
    60.8, Performance tests Yes Except in (d) performance tests involving only Method 9 (40 CFR part 60, appendix A-4) require a 7-day advance notification instead of 30 days (§ 60.675(g)).
    60.11, Compliance with standards and maintenance requirements Yes Except in (b) under certain conditions (§§ 60.675(c)), Method 9 (40 CFR part 60, appendix A-4) observation is reduced from 3 hours to 30 minutes for fugitive emissions.
    60.18, General control device No Flares will not be used to comply with the emission limits.