Table 6 to Subpart PPPPP of Part 63 - Requirements for Reports  


Latest version.
  • Table 6 to Subpart PPPPP of Part 63 - Requirements for Reports

    As stated in § 63.9350, you must submit each report that applies to you according to the following table:

    If you own or operate a new or reconstructed affected source that must comply with emission limitations, you must submit a . . . The report must contain . . . You must submit the report . . .
    1. Compliance report a. If there are no deviations from the emission limitations that apply to you, a statement that there were no deviations from the emission limitations during the reporting period Semiannually, according to the requirements in § 63.9350.
    b. If there were no periods during which the CEMS or CPMS were out of control as specified in § 63.8(c)(7), a statement that there were no periods during which the CEMS or CPMS was out of control during the reporting period Semiannually, according to the requirements in § 63.9350.
    c. If you have a deviation from any emission limitation during the reporting period, the report must contain the information in § 63.9350(c) Semiannually, according to the requirements in § 63.9350.
    d. If there were periods during which the CEMS or CPMS were out of control, as specified in § 63.8(c)(7), that report must contain the information in § 63.9350(d) Semiannually, according to the requirements in § 63.9350.
    e. If you had an SSM of a control device or associated monitoring equipment during the reporting period, the report must include the information in § 63.10(d)(5)(i) Semiannually, according to the requirements in § 63.9350.