§ 35.935-14 - Final inspection.  


Latest version.
  • The grantee shall notify the Regional Administrator through the State agency of the completion of step 3 project construction. The Regional Administrator shall cause final inspection to be made within 60 days of the receipt of the notice. When final inspection is completed and the Regional Administrator determines that the treatment works have been satisfactorily constructed in accordance with the grant agreement, the grantee may make a request for final payment under §35.945(e).