§ 2556.155 - May a sponsor manage a VISTA project through a subrecipient?  


Latest version.
  • § 2556.155 May a sponsor manage a VISTA project through a subrecipient?

    (a) A sponsor may carry out a VISTA project through one or more subrecipients that meet the eligibility criteria of § 2556.100.

    (b) The sponsor must enter into a subrecipient agreement with each subrecipient. A subrecipient agreement must have at least the following elements:

    (1) A project plan to be implemented by the subrecipient;

    (2) Records to be kept and reports to be submitted;

    (3) Responsibilities of the parties and other program requirements; and

    (4) Suspension and termination policies and procedures.

    (c) The sponsor retains the responsibility for compliance with a Memorandum of Agreement; the applicable regulations in this Part; and all applicable policies, procedures, and guidance issued by CNCS AmeriCorps regarding the VISTA program.

    (d) A sponsor shall may not request or receive any compensation from a subrecipient for services performed by a VISTA.

    (e) A sponsor shall may not receive payment from, or on behalf of, the subrecipient for costs of the VISTA assistance, except in two limited circumstances:

    (1) For reasonable and actual costs incurred by the sponsor directly related to the subrecipient's participation in a VISTA project; and

    (2) For any cost share related to a VISTA placed with the subrecipient in the VISTA project.